Why the payment bond exists
On a private job, an unpaid sub can usually file a lien against the property. Government property can't be liened. So Georgia requires a payment bond on most public construction, and that bond stands in for lien rights. If the prime contractor doesn't pay, the people who supplied labor and materials can collect from the surety instead.
State jobs fall under O.C.G.A. § 13-10-60 and the sections after it. City, county and school board jobs fall under O.C.G.A. § 36-91-90 and the sections after it. The claim rules in the two are written almost word for word the same.
Step one: find out if a notice of commencement was filed
Your deadline depends on one document. On public work, the prime contractor is supposed to post a notice of commencement on the job site and file it with the clerk of superior court in that county within 15 days after starting work. It lists the contractor, the project, the government owner and the bonding company.
If you can't find it, ask the prime in writing for a copy. The contractor has 10 calendar days to send it. Keep a copy of your request, because a contractor who doesn't answer can lose the benefit of the shorter deadline below.
The deadlines
| Your situation | Deadline | What to do |
|---|---|---|
| You were hired by a sub, and a notice of commencement was filed | 30 daysFrom the filing of the notice, or from your first delivery of labor or materials, whichever is later | Send written notice to the prime contractor with your name, address and phone, who hired you, the project, and what you are furnishing |
| You were hired by a sub, and no notice of commencement was filed | 90 daysFrom the last day you did work or delivered materials | Send written notice to the prime contractor stating the amount you claim and who you worked for |
| You still haven't been paid | After 90 daysFrom your last work or delivery | You can file suit on the bond once 90 days have passed |
| Suit on the bond | 1 yearFrom completion of the contract and acceptance of the work by the government owner | File the lawsuit in your own name. The government owner is not a party |
The notice has to go by registered or certified mail, statutory overnight delivery, or any method a sheriff can use to serve papers. A text or an email to the project manager does not count.
Who the notice rules apply to
If you had a contract directly with the prime contractor, the notice steps above don't apply to you. You can sue on the bond once you've gone 90 days without full payment. The notice rules are for people one level down: a supplier or sub-sub hired by a subcontractor, with no contract of their own with the prime. If you're further down the chain than that, you may not be covered at all, so talk to a construction attorney early.
Private jobs work differently
Most private jobs don't have a payment bond, so your protection is the lien. The main Georgia deadlines are:
- Notice to contractor: if you don't have a contract with the prime and a notice of commencement was filed, send a notice to contractor within 30 days of the filing or your first delivery, whichever is later (O.C.G.A. § 44-14-361.5).
- Claim of lien: file it with the clerk of superior court within 90 days after you finish the work or deliver the materials. Send a copy to the owner within 2 business days (O.C.G.A. § 44-14-361.1).
- Lien action: start the lawsuit within 365 days of filing the lien, and file a notice of that action within 30 days of starting it.
- Bonded-off liens: an owner or contractor can file a bond to discharge your lien. It must be double your claim (or equal to it on the owner's home). Your claim then moves to that bond (O.C.G.A. § 44-14-364).
Federal jobs follow the Miller Act
Work for a federal agency in Georgia, like a military base or VA facility, falls under the federal Miller Act, not Georgia law. A supplier or sub-sub with no contract with the prime must give notice within 90 days of its last work, and suit must be filed within one year after the last work (40 U.S.C. § 3133).
A checklist that keeps you paid
- Ask for the notice of commencement before you start, in writing.
- Write your 30-day and 90-day dates on the job folder the day you first deliver.
- Keep delivery tickets, daily logs and invoices that show your last day on the job.
- Send notices by certified mail and keep the receipts.
- Put the one-year suit deadline on your calendar as soon as the job is accepted.
If you're the prime contractor
Filing the notice of commencement on time protects you too. It shortens the window for surprise claims from people you never hired. When you need the bonds themselves, see our performance and payment bond page or the bid bond page, or read how contract bonds work.
Bidding public work? See your bond price in 60 seconds on the performance bond calculator, or start a chat below.
Sources: O.C.G.A. §§ 13-10-60, 13-10-62, 13-10-63, 13-10-65, 36-91-90, 36-91-92, 36-91-93, 36-91-95, 44-14-361.1, 44-14-361.5, 44-14-364; 40 U.S.C. § 3133. Deadlines are strict and courts read them closely. This article is general information, not legal advice. For a claim in progress, talk to a Georgia construction attorney.